==Tich's Art of FlatRaising==
 
==Tich's Art of FlatRaising==
  
===Definition:===
+
===Definition===
FlatRaising is a term used to describe the way to get slopes greater than 40 dirt (4 meters).
+
Flatraising is a term used to describe the process of making [[slope]]s greater than 40 dirts (4 meters).
 
 
===Why it is used:===
 
 
 
It is used because dirt "flows" when a slope gets to 40 (4 meters), what i mean by "Flow" is that the dirt will slide down the slope until it gets to a lesser slope.
 
 
 
How to tell what a slope is.. Well examine the Tile border, but dirt will also flow if the diagonal of the tile is over 4 meter slope as well.
 
 
 
===Restrictions:===
 
The largest slope you can make is three times your skill.
 
 
 
===How to do it:===
 
For this example i will assume that you start with a 4x4 (totally) flat area and want to raise the middle 2x2 area up high.
 
  
First drop 40 dirt on each corner of the 2x2 area.  
+
===Purpose===
 +
Dirt "flows" when a slope gets to 40 dirts (4 meters). "Flowing" means that the dirt will slide down the slope until it gets to a lesser slope (less than 40). Dirt will also flow if the diagonal slope of the tile is over 40 dirts (4 meters).
  
Once the outer slopes are 40 dirt, start dropping dirt (batches of 10-20 dirt is good) in the center of the 2x2 and flatten one of the tiles (rotating the tile to flatten is a good idea, if not you had better flatten all the 4 tiles). Remember not to stand on the high point when flattening as you will get "Ouches".
+
===Measurement===
 +
To find out how many dirts (how steep) a slope is, examine the tile border. A [[digging]] skill of 15 or better will allow a "mouseover" examination of the border when a shovel is activated.
  
Repeat until either you get the "Spire" to your desired height or to your skill height.
+
===Restrictions===
 +
The largest slope you can make is 3x your skill.
  
===Notes:===
+
===Method===
Another Option is to dig at the base of a slope to increase it, but this is not always possible (e.g. on landbridges or when doing a road along rock).
+
''For this example I will assume that you're starting with a 4x4 (completely flat) area and want to flatraise the middle 2x2 area.''
 +
# Drop 40 dirts on each exterior corner of the 2x2 area.
 +
# Once the exterior corners are raised 40 dirts, start dropping dirt (batches of 10-20 dirt is typical) in the center of the 2x2 area.
 +
# [[Flattening|Flatten]] one of the tiles (rotating the tile to flatten is a good idea; if not you had better flatten all the 4 tiles). ''Remember not to stand on the high point when flattening as you will get [[wound|"ouchies"]].''
 +
# Repeat until you get the "spire" to your desired height or to the maximum height for your skill level.
  
===Tips:===
+
[[Image:FlatRaising.png|center|460px|The largest slope you can make is three times your skill.]]
Note that once the slope gets over 20 dirt, to get up/down from this 2x2 area will not be easy because you may need to climb.  
 
  
Advice is to make a pile for the dirt (using any object on you, its easier with different items as this will form a "pile of items", which is easier to target) on the slope and then add the dirt (from your cart), and retrieve your items, repeat until your pile(s) have 100 dirt so you don't have to keep climbing up/down.
+
===Variation===
 +
Another option is to dig at the base of a slope to increase it, but this is not always possible (e.g. on landbridges or when building a [[road]] along rock).
  
 +
===Tip===
 +
* Once the slope gets over 29 dirts, you will have [[Climbing|climb]] to get up and down from the 2x2 area. To save time, use this method to prevent you from having to climb up and down the slope as you work: drop items you have in your [[inventory]] (easier with four different items) until you form a "[[pile of items]]" which is easy to target. Then add at least 2 dirts to the pile and remove your items. You may add up to 100 dirts to each pile (one pile per tile).
  
{{cleanup}}
+
===Tutorial===
{{copyedit}}
+
[http://www.youtube.com/watch?v=k60abympbuU Flatraising with Slickshot]
  
[[Category:Guides]][[Category:Babel/F]]
+
[[Category:Guides]]

Latest revision as of 18:39, 15 March 2022

Information icon.png
Note: This article is the opinion or suggestion of one or more players. Information in player-made guides are not maintained by the Wurmpedia staff. It is subject to player opinions, and information may not be factually accurate or up-to-date. For updated game mechanics information, check the main namespace articles.


Tich's Art of FlatRaising

Definition

Flatraising is a term used to describe the process of making slopes greater than 40 dirts (4 meters).

Purpose

Dirt "flows" when a slope gets to 40 dirts (4 meters). "Flowing" means that the dirt will slide down the slope until it gets to a lesser slope (less than 40). Dirt will also flow if the diagonal slope of the tile is over 40 dirts (4 meters).

Measurement

To find out how many dirts (how steep) a slope is, examine the tile border. A digging skill of 15 or better will allow a "mouseover" examination of the border when a shovel is activated.

Restrictions

The largest slope you can make is 3x your skill.

Method

For this example I will assume that you're starting with a 4x4 (completely flat) area and want to flatraise the middle 2x2 area.

  1. Drop 40 dirts on each exterior corner of the 2x2 area.
  2. Once the exterior corners are raised 40 dirts, start dropping dirt (batches of 10-20 dirt is typical) in the center of the 2x2 area.
  3. Flatten one of the tiles (rotating the tile to flatten is a good idea; if not you had better flatten all the 4 tiles). Remember not to stand on the high point when flattening as you will get "ouchies".
  4. Repeat until you get the "spire" to your desired height or to the maximum height for your skill level.
The largest slope you can make is three times your skill.

Variation

Another option is to dig at the base of a slope to increase it, but this is not always possible (e.g. on landbridges or when building a road along rock).

Tip

  • Once the slope gets over 29 dirts, you will have climb to get up and down from the 2x2 area. To save time, use this method to prevent you from having to climb up and down the slope as you work: drop items you have in your inventory (easier with four different items) until you form a "pile of items" which is easy to target. Then add at least 2 dirts to the pile and remove your items. You may add up to 100 dirts to each pile (one pile per tile).

Tutorial

Flatraising with Slickshot